Operating Session 36
jump to photos Click Here
The Fourth Annual 7th Division PNR Modeler's Meet
The Coquihalla Valley Railway
May 3rd 2019
Some memories from at Operating Session #36 on the Coquihalla Valley Railway on Friday afternoon May 3rd 2019
Session Summary
CQVR #36 Operations images & text copyright John Green
Train crews for Layout Date September 24, 1955
Your CQVR host crew
Session Summary
The Layout Date was Tuesday September 13th, 1955
The fast clock started at 0545 am – stopped 18:00
14 trains were operated
10 Train Orders issued
23 Clearances issued
Approximately 140 freight cars moved
10 Passenger cars plus 4 head end cars moved
4 Trains were “still on the road” at the end of the session
The Coquihalla Valley Railway
May 3rd 2019
Some memories from at Operating Session #36 on the Coquihalla Valley Railway on Friday afternoon May 3rd 2019
Session Summary
CQVR #36 Operations images & text copyright John Green
Train crews for Layout Date September 24, 1955
| Brookmere Yard Master | Burr S |
| Coquihalla Way Freight | Dave L |
| Juliet Logger | Dick S |
| Nicola Turn | Jake S |
| No 93, No 806 and No 805 | Anne-Marie L |
| No 79, No 11, and No 82 | Stuart C |
| No 80, No 12, and No 81 | John S |
| Dispatcher | Brian D. |
| Operator Brookmere and Merritt | Anne P |
| Operator Coquihalla and Hope | Ken M |
| Operator Portia and Terminals | Anthony C |
| Host and Trainmaster | John Green |
| Photographers | John S, Sharon G, John G |
The Layout Date was Tuesday September 13th, 1955
The fast clock started at 0545 am – stopped 18:00
14 trains were operated
10 Train Orders issued
23 Clearances issued
Approximately 140 freight cars moved
10 Passenger cars plus 4 head end cars moved
4 Trains were “still on the road” at the end of the session